Skanska signs additional contract with existing client to build a data center in USA for USD 228M, about SEK 2.2 billion

The project involved constructing high bay areas for data halls, electrical rooms, mechanical rooms, loading dock, office and storage areas.

The supplemental award increases the total contract value to USD 267M. The original award of USD 39M was for early work on the project.

Construction began in the fourth quarter of 2025 and is expected to be completed in 2027.  