Skanska allocated an additional GBP 71M, about SEK 940M, towards works on the high-speed railway HS2 in UK

The award relates to planned and agreed changes to the scope of works under the contract.

The total contract, now valued at approximately GBP 1.4 billion, about SEK 18.5 billion, to Skanska, involves the design and construction of major tunnels in the southern section of the overall project.

Since being given notice to proceed by HS2 Ltd in April 2020, significant progress has been made. Two tunnel boring machines (TBMs) started operations in late 2022 from West Ruislip Portal towards Green Park Way - to date completing around 2.9km of their 8km journey. Two further TBMs have been received in the UK and will be launched early in the next year from Victoria Road Crossover Box. A third TBM is in operation from Atlas Road, constructing a logistics tunnel between Old Oak Common station site and the Atlas Road site. The preparation works for the launch of the two final TBMs from the Old Oak Common Box towards Euston will begin in 2024. 

Datum 2023-12-15, kl 07:30
Källa Cision
Bifogade filer
Vill du synas här? Kontakta hej@allaaktier.se. Vår sajt har 100 000 sidvisningar och 15 000 unika besökare per månad. Vår discord har över 6000 medlemmar. Detta är aktiva sparare med ett stort aktieintresse. Behöver du nå ut till denna målgrupp så hör av dig!