Citylink is part of Svenska kraftnät’s initiative to future-proof the electricity supply in the Stockholm region by connecting the power grid between northern and southern Stockholm. Bravida’s work will be carried out along the 13-kilometre tunnel section between Anneberg and Skanstull, where the deepest section is located approximately 100 metres underground.
“Bravida’s Citylink assignment strengthens our leading position in large, complex installation projects within critical infrastructure. Projects like this require extensive experience, specialist expertise and strong collaboration skills,” comments Lars Täuber, Head of Division Sweden at Bravida.
Work began in October 2026 and is expected to be completed in June 2028. The order was registered in Bravida’s order intake in the third quarter of 2026.